📞 +91 98122 41001 ✉ info@kelvinindia.in 💬 WhatsApp
NSICMSMEISO 9001/14001/45001BISGeM-OEMCSIR-CMERIZED Pledged
K-Recover · Material Recovery Facility

Turnkey MRF lines — 5 to 100 TPD.

Dry-waste sorting facilities with manual + mechanical separation, K-BPM 25 / 50 baling presses, and EPR-aligned operations. Built for ULBs, private brands, recycling consolidators and PPP operators.

Standard MRF line scope

  • Receiving belt + manual picking station
  • Bag opener (auto or manual depending on TPD)
  • Trommel screen (60 mm + 200 mm decks)
  • Magnetic separator (overband)
  • Eddy current separator (non-ferrous, > 50 TPD)
  • Air density separator (light/heavy split)
  • Optical sorter for PET/HDPE colour separation (> 80 TPD)
  • Quality control conveyor
  • K-BPM 25 baling press (small MRFs)
  • K-BPM 50 baling press (large MRFs / export-grade bales)
  • Bale storage shed with weighbridge
  • PLC + SCADA control system

Typical output streams

  • PET / HDPE bales (~10–15%)
  • Paper / cardboard bales (~15–20%)
  • Aluminium / metals (~3–5%)
  • Plastic film & multi-layer (~5–8%)
  • Organics fraction routed to compost (~30–40%)
  • Inerts & rejects to SLF (~15–25%)

Compliance

  • SWM Rules 2016
  • PWM Rules 2016 (2022 amendment)
  • EPR registration on CPCB portal
  • State PCB CTE / CTO
  • GST classification 3915 for recycled scrap
Right-sized MRF

Three typical configurations

Small MRF · 5–25 TPD

Manual sort + magnetic + air density + K-BPM 25. Footprint ~0.3 ac. CapEx ~₹2–6 Cr.

Mid MRF · 25–50 TPD

Adds eddy-current + ballistic separator + K-BPM 50. Footprint ~0.6 ac. CapEx ~₹5–12 Cr.

Large MRF · 50–100 TPD

Optical sorter + multi-line + automated bale handling. Footprint ~1.2 ac. CapEx ~₹14–30 Cr.

Building a tender for an MRF?

We supply BOQ-ready spec sheets for every component.

Configure via wizard →
Project timeline

From DPR to commissioning — typically 14–22 weeks

MRF projects move faster than waste-treatment plants because there's no CPCB SOP-mandated trial run. Below is a typical schedule for a 25 TPD K-Recover MRF.

DPR & site survey

Material flow study · land area · electrical load · 1-2 weeks

State PCB CTE

Consent-to-Establish · 4-6 weeks (parallel to design)

Civil & foundation

Concrete pad · sheds · wash bay · weighbridge · 6 weeks

Manufacturing

Trommel + separator + balers + conveyors at Manesar · 10 weeks

Erection & install

On-site assembly + electrical + automation · 3 weeks

CTO + handover

Consent-to-Operate · staff training · 1 week

FAQ

Common MRF buyer questions

K-BPM 25 vs 50 — which baler for my MRF?

K-BPM 25 (25-ton vertical hydraulic) is the right pick for MRFs processing <5 TPD dry-waste with PET / paper / cardboard / HDPE; bale density 300-500 kg/m³. K-BPM 50 (50-ton heavy-duty) for >5 TPD throughput, dense scrap (e-waste, mixed metal), or export-grade bale density (400-600 kg/m³, 4-strap binding). See K-BPM 25 vs K-BPM 50.

What's the revenue picture?

Indicative dry-waste recyclate prices (2026): PET ₹35-45/kg · HDPE ₹40-55/kg · cardboard ₹15-20/kg · paper ₹12-18/kg · mixed metal ₹35-90/kg. A 25 TPD MRF processing 60% recyclables typically generates ₹3-5 lakh / month gross recyclate revenue, plus EPR plastic-credit revenue from registered offtake.

How does this work with EPR registration?

An MRF registered under the CPCB EPR portal can issue plastic credits to brand owners (FMCG, e-commerce, packaging companies) under PWM 2016 (am. 2022) — adding ₹3-8 / kg revenue on plastic offtake. We help structure the EPR registration and brand-owner offtake agreements at DPR stage.

What's the manpower requirement?

25 TPD MRF: 18-24 sorters (mostly women SHGs in ULB context) + 1 supervisor + 2 baling-press operators + 2 trommel/conveyor operators + 1 maintenance + 1 dispatch coordinator. Manual sorting at the picking belt is the labour-intensive piece; mechanical separation via trommel + magnetic separator + ballistic separator handles 60-70% of volume.

Land area required?

5 TPD: ~1,000 sq m · 25 TPD: ~3,500 sq m · 50 TPD: ~5,500 sq m · 100 TPD: ~9,000 sq m. Add 30-40% for parking, weighbridge, fire pit, office. The exact figure depends on covered shed vs open yard split — finalised at DPR.

Lead time and AMC?

Manufacturing 10 weeks ex-Manesar. Total project (DPR to commissioning) 14-22 weeks. 1-year comprehensive warranty + AMC from year 2. Engineer on-site within 24-48 hr. Spare parts same-day ex-Manesar.